ABSTRACT

The open pit Veliki Krivelj is a copper mine which operates within RTB Bor Group in
Serbia. In 1998 a combined haulage system involving the initial dump truck haulage,
crusher, belt conveyor and a boom spreader for waste disposal was designed and
installed in order to reduce the costs on overburden removal. The designed productivity
of the system is 4 700 t/h and it will be fully operational in the next few weeks. Up to date it has been capable of achieving maximal 50% of this productivity because only one of two designed crushers was installed.
This paper gives an overview of the achieved annual productivities of the system in the
period from 1998 to 2010 as well as the necessary explanations of the reasons of the low
productivity utilization. The presented data can be useful to those mining experts who
are considering implementation of similar combined haulage systems.

Keywords: RTB Bor Group, Veliki Krivelj, overburden haulage, combined system

PAPER 2011/s03.134: REVIEW OF THE ACHIEVED PRODUCTIVITY OF THE COMBINED OVERBURDEN HAULAGE SYSTEM AT THE VELIKI KRIVELJ OPEN PIT - SERBIA

30 EURO ADD TO CART


Your cart ( items)

Subtotal:
Tax cost ():
Shipping cost:
Total:
Checkout Empty